Sakhalin-2 LNG postpones part of maintenance to 2021 -source
Russia’s Sakhalin-2 liquefied natural gas (LNG) plant will postpone some annual maintenance work to 2021 due to logistic difficulties over the spread of the coronavirus, a source familiar with the plans told Reuters on Tuesday.
Russia’s second-largest LNG plant after Novatek-led Yamal LNG had initially planned to complete the work this summer.
However, the source said the maintenance would be done gradually, at one of two lines and start in June. The first stage of the maintenance would last about a month, the source said.