The Business: Shell field off Nigeria risks more delays
“Royal Dutch Shell’s flagship $2.7bn (£1.5bn, €2.2bn) Bonga project off Nigeria is believed to be suffering damaging delays, just a week after the company stunned investors by doubling the costs of its Sakhalin gas project to $20bn.”
Sunday July 24, 2005
By: Richard Orange
Royal Dutch Shell’s flagship $2.7bn (£1.5bn, €2.2bn) Bonga project off Nigeria is believed to be suffering damaging delays, just a week after the company stunned investors by doubling the costs of its Sakhalin gas project to $20bn.
The company last week signed up the accommodation vessel for project workers for an extra five months until March, indicating that considerable work is still needed on the floating production platform beyond the latest target for first production in October.
Jonathan Wright at Citigroup told The Business: “It’s very suspicious. It looks as though it’s potentially a risk.”
Shell said it still expected first production from the 225,000 barrel per day project in the third quarter this year, with the additional staff mainly needed for painting work.
But Robin Laird, president of Prosafe Offshore, which is supplying the floating hotel, said the vessel was needed to house staff to “assist with the further modification to the Bonga vessel itself. It’s being upgraded. There’s still lots more engineering to do.”
An analyst, who declined to be named, said: “It seems surprising that the company is maintaining its third-quarter forecast at the same time as it’s contracting this accommodation vessel for several months longer. It suggests it is still going to have a lot more people working to complete the final project than they would have expected. What they’ll do is they’ll commission it, get it producing and then they’ll shut it down again to finish it off.”
Bonga was initially expected to begin production at end-2003. Shell refuses to provide an update, but the $2.7bn initial cost of the project is believed to have soared to at least $3.5bn.
This website and sisters royaldutchshellplc.com, shellnazihistory.com, royaldutchshell.website, johndonovan.website, and shellnews.net, are owned by John Donovan. There is also a Wikipedia segment.
















Royal Dutch Shell conspired directly with Hitler, financed the Nazi Party, was anti-Semitic and sold out its own Dutch Jewish employees to the Nazis. Shell had a close relationship with the Nazis during and after the reign of Sir Henri Deterding, an ardent Nazi, and the founder and decades long leader of the Royal Dutch Shell Group. His burial ceremony, which had all the trappings of a state funeral, was held at his private estate in Mecklenburg, Germany. The spectacle (photographs below) included a funeral procession led by a horse drawn funeral hearse with senior Nazis officials and senior Royal Dutch Shell directors in attendance, Nazi salutes at the graveside, swastika banners on display and wreaths and personal tributes from Adolf Hitler and Reichsmarschall, Hermann Goring. Deterding was an honored associate and supporter of Hitler and a personal friend of Goring.
Deterding was the guest of Hitler during a four day summit meeting at Berchtesgaden. Sir Henri and Hitler both had ambitions on Russian oil fields. Only an honored personal guest would be rewarded with a private four day meeting at Hitler’s mountain top retreat.














IN JULY 2007, MR BILL CAMPBELL (ABOVE, A RETIRED GROUP AUDITOR OF SHELL INTERNATIONAL SENT AN EMAIL TO EVERY UK MP AND MEMBER OF THE HOUSE OF LORDS:


MORE DETAILS:












A head-cut image of Alfred Donovan (now deceased) appears courtesy of The Wall Street Journal.